Simultaneous Data Center Upgrades Across Four US Locations

Millennial Asia young call center team or customer support service executive using computer and microphone headset working technical support in late night office. Telemarketing or sales job concept.

Executive Summary

A leading global telecommunications company needed to upgrade their legacy equipment to new Cisco carrier grade infrastructure and required a technology partner capable of quickly assembling multiple skilled engineering teams to upgrade and simultaneously deploy the solution at four data centers across the US.

Arrow left Resources

The Challenge: Simultaneously Upgrading Data Center Legacy Equipment Across Four Different US Locations

A leading global cable and backbone internet provider needed to simultaneously upgrade their legacy backbone routing equipment with new Cisco carrier grade infrastructure across four of their US data centers. Due to issues with the legacy equipment, the project needs to be completed and brought online simultaneously. The client needed a partner with the skill and reach to quickly get up to speed on the project and be able to deploy teams in New York, NY, Dallas, TX, Chicago, IL, and San Jose, CA. They also needed a partner that could provide the oversight and project management necessary to coordinate and manage all four projects concurrently.

The Solution: Assembling Multiple Skilled Engineering Teams with Project Management Across Various Locations

The client, in collaboration with a leading technology partner, selected Judge Consulting to partner on the data center upgrades in all four locations. Judge was selected because of their prior experience working with larger data center build outs, their expertise across a range of networking technologies, their ability to provide meticulous project management, and their national reach being able to assemble skilled engineering teams in multiple locations across the country. Judge met with the client project owners, technology partner SMEs, and key stakeholders to review and agree on the necessary rack elevations, patch schedules, power layout, and equipment to deploy.

The Result: Successful Deployment of Data Center Upgrades Allowing for Simultaneous Turn Up at All Four Sites

Judge was able to quickly assemble and scale multiple teams across the client’s four data centers in New York, NY, Dallas, TX, Chicago, IL, and San Jose, CA. The Judge team physically installed the racks with the supplied equipment, labeled all connections, and documented f inal patching solutions concurrently. Additionally, Judge loaded basic configuration files onto all equipment and successfully verified remote accessibility from the client NOC team. This allowed the client to cut over from their legacy equipment to their new Cisco carrier grade infrastructure and bring all four locations online simultaneously and without issue.

Related Case Studies

Global Financial Institution Looks to Judge’s Business Process Optimization Team to Uncover and Document Critical Process Workflows

THE CHALLENGE: Capturing Critical, Undocumented Processes  The client, a global financial institution, relied heavily on complex internal processes central to its operations—but the knowledge lived only within a few key individuals. Without formal documentation or visibility…

Global Financial Institution Looks to Judge’s Business Process Optimization Team to Uncover and Document Critical Process Workflows

Modernizing a Complex Mobile Application to Overcome User Experience and Content Gap Challenges

A leading provider of psychological assessment tools needed to modernize and improve their mobile application amid growing technical bugs and user experience issues that were causing poor customer satisfaction and declining engagement.

Modernizing a Complex Mobile Application to Overcome User Experience and Content Gap Challenges

From Service to Systems — How Judge Helped Veterans Power a Financial Institution’s Mainframe Revival

The Challenge: A Shrinking Talent Pool and Overlooked Potential The financial institution’s Consumer Technology division faced a growing crisis: the aging out of Mainframe programmers and a lack of new talent to maintain legacy systems essential to daily banking operations.

Woman sitting at a desk smiling with American flag in background